We actually have the rebuild of the hardware in a possible "shell" site
documented.  Teams are organized with specific tasks.  The "shell" site
has a double move built in - from hot site to shell then to new home.
But not the actual mechanics.  Which, as Dave suggests, is pretty much a
reverse.

Our desktop drill involved a building power problem and our data center
was intact.  The power problem would have the building down for 3 to 5
weeks.

The actual disaster I went through in the 80s was a phone problem.  We
lost all phones at corporate and the T1 between our data centers.  Our
DR plan was to flip the data centers and then we just flipped them back
after the T1 came up.  Took about 3 or 3 1/2 weeks.  There's a write-up
in a 1988 Computerworld on what we did (of course the top guys gook all
the credit).

I don't have the luxury of 2 physical locations here.  Replication would
add another dimension too.  Hmm..

 --------------------------------------------
Andy Engels
IS Team Leader - Technical Services
Illinois Municipal Retirement Fund
Oak Brook, IL
630-368-5346 


-----Original Message-----
From: owner-vse-l@Lehigh.EDU [mailto:owner-vse-l@Lehigh.EDU] On Behalf
Of Allan Peterson
Sent: Tuesday, August 18, 2009 9:42 PM
To: VSE Discussion List
Subject: RE: DR - Going Home Again


Yep

Tell HUR to start replicating to home ... 24 hours later IML/IPL  ...

The gotchas...

Home to be defined , possibly built , new network etc installed , source
replacement processor for home 

-----Original Message-----
From: owner-vse-l@Lehigh.EDU [mailto:owner-vse-l@Lehigh.EDU] On Behalf
Of Andy Engels
Sent: Wednesday, 19 August 2009 10:21 a.m.
To: VSE Discussion List
Subject: DR - Going Home Again

Hi all.........

Question 1: Do any of you have written procedures for going home again
after a Disaster? 

Question 2: Has anyone actually practiced this - at least the part where
you pick up your stuff from the hot site?


We're in the midst of updating the organization's Business Continuity
Plan again.  We do little updates but this is the annual major update
after our latest desktop drill.

We have a semi-informal "just run the dr plan in reverse" plan which I
think needs formal documentation.

Thanks...........



 --------------------------------------------
Andy Engels
IS Team Leader - Technical Services
Illinois Municipal Retirement Fund
Oak Brook, IL
630-368-5346 


New Message Reply Date view Thread view Subject view Author view Other groups

This archive was generated by hypermail 2b25 : Wed Sep 02 2009 - 20:20:10 EDT